|
|
Port of East London Quay Wall Requires Strengthening

|
|
Owen Hensburg has been with the South African National Ports Authority (NPA) for twenty-eight years, and has survived many industry changes in the last decade.
|
|
|
The NPA is owned and controlled by Transnet and has
the government as sole shareholder. The various
divisions within Transnet consist of amongst others,
Spoornet, SAA, Petronet, and the old Portnet, which
has since been split into SA Port Operations and the
NPA, and looks after port infrastructure.
“The engineering department within the NPA deals
largely with civil engineering and structural building
projects and therefore our role as Engineering
Technicians has evolved to become that of project
managers,” explains Owen.
Projects are mostly completed with the help of
AllyCAD, while Civil Designer is used for road
rehabilitation projects. “In a small port such as
ours, there are very few big roads and our road
rehabilitation projects are therefore not large,” says
Owen, adding that as part of the committee for Port
Development Planning, they use AllyCAD extensively
when working with the Industrial Development Zone (IDZ)
areas, and the Port Development Framework Plan.
Strengthening of the West Quay
The strengthening of West Quay was necessitated by the
increase in the draft of car carrier ships, and in
anticipation of the increased import and export
activity by DaimlerChrysler SA in May 2003.

“The 14-metre high quay wall (from foundation to top
of quay) required strengthening so that contractors
could dredge the river deeper and closer to the quay
footing. This was necessary to create more depth for
deeper drafted ships to berth alongside the quay.” |
|
|
"The scope of work covered the strengthening of
approximately 254-metres of the West Quay. This was
done through a combination of rock anchors, and the
construction of a reinforced concrete extension to the
coping beam overhanging the water by 1,5metres, and
1,2metres in depth. We cast fendering units integrally
with the extended cope beam at 8,7m centres, extending
a further 2m below the soffit of the cope beam and
each 4,5m in length.
“Our in-house contractor, Protekon, was appointed to
do the work. They used a purpose made mobile scaffold
on tracks to form the reinforced concrete cope beam.
Once this was completed, we proceeded to drill 160mm
diameter holes at a 30-degree angle through the cope
beam, quay wall, and finally, into the rock.”
“We then inserted rock anchors ranging from 19-metres
to 28-metres in length, into the drilled holes. The
porosity of the rock had to be tested in each hole
before the anchors were inserted, grouted up, tested
and finally tensioned. We installed 41 anchors in
total,” explains Owen.
“The quayside extension has been completed, but the
dredging activity using a rock grab, will continue
until the berthing depth of 10,7-metres has been
attained, ” says Owen adding that the 254 metre quay
wall extension took seven months of construction and
cost in the region of R8,4 million.
Dredging Service
Owen elaborates further on the dredging service that
the NPA provides. “Currently, we have two dredging
campaigns, a summer campaign and a winter campaign. We
are allowed access to a designated disposal site once
we have acquired the necessary disposal permits.” |
|

|
“We have a sand trap of 20 metres deep, with a 14
metre deep entrance channel, and we need to maintain
this navigation area which usually results in
approximately 550 000 tons of sand being dredged per
year. It is also far easier to dump material than to
use it for fill purposes, as this adds to the cost of
dredging” explains Owen.
The dredger “Piper” visits from Durban twice a year
and the dredging activity is accompanied by
hydrographic surveys. This is where a designated
person surveys the water’s depth with the use of an
Echo Sounder and GPS.
|
|
Specialised equipment is used to do the lead line
soundings, so that the data is collected and input
into Civil Designer’s Survey & Terrain module. Once
all the values have been entered into the program,
Owen is able to get an accurate model of the area with
exact dimensions and volumes to be dredged.
Conceptual Drawings
The NPA has recently assisted with the conceptual
drawing plans for a new car terminal. “The area was
previously an old quarry that had been used as a
container parking area. The multi level car terminal
can house approximately 2 800 vehicles, and has a
dedicated road from the DaimlerChrysler factory.”
“It also boasts a container area where assembled
vehicles are placed in the empty containers in which
the car parts arrive, so that the contained vehicles
may later be exported. Each 12-metre container
comfortably accommodates three vehicles. The
conceptual plans of the car terminal were completed
with the help of AllyCAD, in accordance with space
availability, and the maximisation of traffic flow. I
find that the program is incredible and we use it
daily to complete our projects.”
Owen displays some of his designs in order to
illustrate the scope of these projects, and judging
from the pride and enthusiasm that he exudes, it is
clear that he wouldn’t trade places with anyone else
in the world.
|
|
|
Last Updated:
August 22, 2005
|