 |
 |
|
|
Developing Projects in the Free State
|
|
|
|
|
HARRISMITH is bustling with activity as the
Phuthaditjhaba and Qwa Qwa regions are placed in the
spotlight for development projects. The design and
implementation of the venture was requested by the Maluti-a-Phofung Municipality in the beginning of
2003 and involves the stormwater management of these
areas as well as the construction of a number of
gravel distributor roads.
Phuthaditjhaba is located in the north eastern Free
State Province and is bounded by Kwa-Zulu Natal to the
southeast and Lesothu to the southwest. It has a total
estimated population of 450 000 individuals and
combined with Qwa Qwa, Harrismith and Kestrel, forms
part of the Maluti-a-Phofung Municipality in the Thaba
Mofutsanyana District Council.
Ninham Shand Consulting Engineer was appointed to
handle the design and contract management of the
project. “The road that we constructed in the Qwa Qwa
area is 10,3 km in length, of which 9700 meters
include stormwater channels with road crossings,” says
Rudi Beeslaar from Ninham Shand.
“The Phuthaditjaba area was equally challenging, as we
constructed a 12,2 km road and the length of
stormwater channels with road crossings was 9500
meters in total. We installed approximately 100 meters
of stormwater pipes with manholes and outlet
structures,” explains Beeslaar, illustrating the scope
of the project.
The topography of the region ranges from steep
mountainous slopes with numerous valleys in the south,
to rolling hills in the north, while the existing
network of roads vary from tarred roads, to two-wheel
tracks.
Interactive engineering design software called Civil
Designer was used to design the horizontal and
vertical road alignments. “The horizontal alignment
was governed by the town-planning layout of the area,
while the vertical alignment was designed to follow
the topographical features |
 |
|
with some
adjustments in order to control the storm water
run-offs.”
“In terms of stormwater systems, concrete stormwater
side drains and road crossings were constructed while stormwater pipes with manholes and outlet structures
were created when required”.
Landscape problems hampered the development of the Qwa
Qwa road, as the houses were built with no formal
structure. This presented a great challenge for the
design of the road because it had to be woven
in-between existing homes and the team often had to
work with steep gradients.
According to Beeslaar, the Qwa Qwa ward councils
specify firm guidelines in maintaining standards and
act as a medium between the community and the
developer during the project’s completion. The design
was completed in accordance with the design criteria
as set out by the Maluti-a-Phofung Municipality and in
accordance with the “Guidelines for the Provision of
Engineering Services and Amenities in residential
township development” manual.
Community reaction on the project was very positive
because the undeveloped area was previously
inaccessible, making transportation impossible. “With
the new road, everyone’s lifestyle will improve
because people will have the benefit of using taxis,
buses and vehicles for transportation to various
destinations,” explains Beeslaar.
The team at Ninham Shand has supported the
government’s job creation initiative by ensuring that
tasks are as labour intensive as possible. Besides
layer works that are completed by machines, |


the rest
of the activities are done by means of manual labour.
The Qwa Qwa region is divided into various wards and
local workers are used within each ward so that the
community can obtain maximum benefit from the project.
In addition to this, material is sourced locally and
it is likely that the road paving will be received
from Lancaster, a factory in Qwa Qwa that is
responsible for the manufacture of bricks. Storm water
pipes will also be sourced locally.
The project has been divided into two phases, with
phase one receiving a budget of R1,2 million for the
creation of 470m of paved road with stormwater
drainage. Phase two will commence shortly and is
expected to receive a budget of R5 million for the
completion of the remaining 1,6km stretch that will
include paving as well as storm water systems.
All earthwork calculations are done in Civil Designer
before the information is transferred into AllyCAD in
order to complete the finishing touches to the design. |
|
Computer Graphics (CG)
August 2004
pg 14 |
|
|
Last Updated:
August 29, 2005
|
|
|
 |