 |
 |
|
|
|
|
WHEN it comes to sports complexes, there are many
complications attached to the allocation of land and
D.G. Naidoo & Associates is only too familiar with all
the restrictions.
This Durban based company looks at the entire layout
for complexes, from sports fields, soccer fields and
combo courts, to change rooms and public facilities.
They also act as advisors to the Department of Sport
and Recreation and evaluate projects to see that
facilities are practical, viable and suited to the
needs of the community.
“On average, I travel about 10 000km per month to
assess the existing and potential sports facilities in
deep rural areas.” says Dees Naidoo owner of Durban
based D.G. Naidoo & Associates. Dees is largely
involved in the infrastructural development of
underprivileged communities, particularly the road
works and the allocation of sports facilities in
KwaZulu Natal.
There is a lot involved when assessing sports
facilities. “We look at existing services, the number
of sports clubs in a given area, the composition of
sports associations and the availability of a sports
counsel. When a rural community needs a sports field,
they simply pick out a spot and then once it has been
cleared, they mark it with four poles and then play
league matches. It’s a big shame, but with the
upgraded facilities, we hope to build a proper 90 X 65
m² sports complex complete with irrigation,” says Dees
with conviction.
According to Dees, there are many complications
attached to the allocation of land. The ‘Inkosis’ or
big chiefs own the land in rural areas and they are
very reluctant to part with it. So when the community
submits their request to the local municipality for a
sports complex, priority projects give rise to the
‘Permission to Occupy’ (PTO) agreement. In this
agreement, the ground is leased to the local
municipality for a set period of time, so the
‘Inkosis’ get to keep ownership of the land creating a
win-win situation. |

Before (February 2004) - this is a sports facility?
This photo provides an indication of the enormity of
the task. |
|
Once land has been identified, the viability for
sports use is tested and various factors are taken
into account. These factors include road access, the
availability of drinking water, sanitation and
sufficient water facilities. If there are no services
planned for the area, a feasibility test is conducted
for future installation. These cost figures are then
included in the budget.
Labour components on the project are very specific and
are strictly controlled by the Monitoring Management
Information System (MMIS). “It is almost impossible to
outsmart the MMIS and penalties are levied to
contractors who do not conform to requirements,” says
Dees. The program specifies that 30% of the
construction cost be given to local contractors and labour. In addition, 50% of the workforce must be
female, 30% must consist of youth members between the
ages of 18 and 35, and 1,5% must be physically
challenged. In a project of between R1 to 2 million,
the total labour force employed on a rotational basis
range between 50 and 80 people for a period of 5 to 9
months.
In order to ensure that there is effective
communication across all parties, the community,
through its various councillors elects a project
steering committee. This body is responsible for
liaising with the community and providing much needed
input on new project developments. New projects are
then communicated once a year via road shows and by
means of electronic media like radio and television.
“We use an interactive design package called Civil
Designer to plan the landfill sites and also to design
the access roads. I am |

After (May 2005) - a new clubhouse

After (May 2005) - a new netball court

After (May 2005) - new changing facilities
very happy with the program. I even lectured Civil
Designer for two years at Mangosothu Technikon and
have been using the program since the early days of
Stardust. I am pleased to have trained the Technikon’s Head of Faculty on this
amazing program and would recommend it to anyone,”
notes Naidoo.
Sports complexes that have been completed by D.G.
Naidoo & Associates include Manguzi, Bambanana and
Sundumbili. “Our goal as a medium sized consultancy is
to grow to a well-established concern with a good
track record. Sports complexes currently range between
R1,5 and R2,5 million and they are a huge improvement
from the informal facilities previously erected by
residents,” says Dees in closing. |
|
Computer Graphics (CG)
June 2004
pg 13 |
|
|
Last Updated:
August 22, 2005
|
|
|
 |